Situation:
Site excavations and complex multi phase shoring system for electrical upgrades for Bridgeport Hospital.
Challenges:
-
Busy urban hospital setting
-
Tight working environment in hospital courtyard
-
Removal of non-hazardous contaminated soils
description:
Working with Turner Construction Company, Brennan performed mass excavations and site work for electrical upgrades in a busy, urban hospital setting. The work included multi-phase excavation and shoring systems for utility upgrades, as well as the removal of non-hazardous contaminated soils. Restoration and paving of site to customer specifications completed the project.